  1. Name the symmetrical and unsymmetrical faults.
  2. A generator supplying an unbalanced load measures the following phase to ground voltages. Va = 16.0∟00 KV, Vb = 15.0∟-1520 KV, Vc = 10.0∟1000 KV. Find the symmetrical components of the set of phase voltages.
  3. What do you understand by instantaneous maximum momentary current for line? Explain it with the help of suitable diagram and drive condition of doubling effect.
  4. For a single line to ground fault at the terminals of an unloaded generator, positive sequence current was found to be 50 A. Determine sequence currents in phase b and c.

2017-18

  1. Derive the relationship to determine the fault current for a single line to ground fault. Draw an equivalent network showing the interconnection of sequence networks to stimulate LG fault.

2016-17

  1. Rank the various faults that can occur in power system in the order of severity.
  2. Prove that 1+ α + α2 = 0. The symbols having their usual meanings.
  3. Define the symmetrical components.
  4. Discuss the principle of the symmetrical components. Derive the necessary equation to convert phase quantities into symmetrical components
  5. The line to ground voltages on the high voltage side of a step up transformer are 100 KV, 33 KV and 38 KV on phases a, b and c respectively. The voltage of phase a leads that of phase b by 1000 and lags that of phase c by 176.50. Determine analytically the symmetrical components of voltage.
  6. Derive the expression for the symmetrical components of fault current of a power system for L-L fault through impedance. A 30 MVA, 11 KV generator has Z1=Z2= j0.2 pu, Z0=j0.05 pu. A-line to ground fault occurs on the generator terminals. Find the fault current and line to line.

2015-16

  1. The neutral grounding irnpedance Znappears as 3Zn in the zetro-sequence equivalent circuit why?
  2. Name the fault current in wtrich all the three sequence currents are present and are equal.
  3. Prove that zero sequence network is absent in case of ocrurence of double line fault through certain impledance in a power system network. Draw the zeto sequence network for the system shown below in figure